When a use is allowed by right, a project that meets the zoning code is approved by staff, with no public hearing and no council vote. For data centers, that has meant fast, predictable approvals. It's also how Loudoun County, Virginia became Data Center Alley.
That's changing. In 2026, GatherGov's meeting data shows 24 cities and counties tightening their rules so data centers can no longer be built by right. Most haven't banned data centers. They've decided they want a say on each project.
Here's what by-right data center zoning means, where it's ending, and what Loudoun's experience says about what comes next for developers.
# What by-right data center zoning means
Under by-right zoning, a use is listed as permitted in a zoning district. If projects meet the code's objective standards, such as setbacks, height and parking, staff have to approve them. There's no public hearing, and neighbors usually aren't notified.
The alternative is discretionary approval. Depending on the state it's called a special exception, a conditional use permit or a special use permit. Each one sends projects to a public hearing, and a board decides, often with conditions attached.
For data center development, that difference sets the timeline. By right, it's driven by plan review. Without it, it's driven by a meeting calendar and a board majority.
# Where by-right data center zoning is ending
GatherGov tracks data center policy across thousands of city council and county board meetings. As of November 2026, our data shows 24 places that changed their rules in 2026 so data centers can no longer be built by right.[1] New Jersey leads, followed by Virginia and Florida.
![]()
The pace picked up through the year: two places made the change in the first quarter, eight in the second, eleven in the third, and three so far in the fourth.[1] We're zooming in on three of them to show what ending by-right looks like and what this means for data center development.
Want all 24 places, with dates and what changed in each? Reach out to us for the full list.
# Manalapan, New Jersey: from by right to off the list, for now
Manalapan Township allowed data centers by right in its commercial, industrial and office districts. On Aug 12, 2026, the Township Committee voted 5–0 to remove them as a permitted use, so the township could look at their impact on land and on water and electric utilities.[2] Explaining the ordinance to residents, Township Attorney Roger J. McLaughlin said:
![]()
New Jersey law explains why towns there take this route. The state bars moratoriums on development applications unless a qualified health professional certifies a clear and imminent danger to public health, and even then caps them at six months.[3] So when a New Jersey town wants time to study data centers, taking them off the permitted-use list is the tool it has. That's one reason New Jersey leads our count, with seven places.
New Jersey's other six places went further, removing data centers as a permitted use in every zone, so a developer's only route is a use variance from the zoning board.[1] Elsewhere, towns are limiting where data centers can go rather than whether: see which towns allow them only in certain districts.
# Orange County, Virginia: from by right to a special use permit
Orange County allowed data centers by right in its General Industrial (I-2) district. In January 2026 the Board of Supervisors started a zoning text amendment, ZTA 26-01, to remove data centers as a by-right use in every district. The Planning Commission recommended it unanimously on March 5, and the board adopted it 5–0 on April 28, 2026. Data centers are now permitted only in the county's new Technology (T) district, and only with a special use permit.[4]
![]()
Most of the board's debate was about the definition. Under the new text, any data center over 10,000 square feet, or one built to serve multiple unaffiliated customers, counts as a principal use "regardless of how it is characterized."
Supervisor Jason Capelle, who proposed the new definition, said the aim was to make sure "no data centers slip through and avoid our requirements," while "a legitimate office building that we may really want to have here doesn't get discouraged because they have a small data center."[4]
# Denison, Texas: from by right to a conditional use permit
Denison's zoning code dates from 2009, when a data center meant something closer to a fiber switchboard. Going through the city's use chart in spring 2026, planning staff found that:
![]()
Data centers had been allowed by right in five districts: regional retail, commercial, business park, light industrial and heavy industrial. On May 18, 2026, the council removed by-right approval altogether. Data centers are now allowed only in the light and heavy industrial districts, and only with a conditional use permit. The city also created a separate "telecommunications facility" use, so the small fiber hubs already in neighborhoods wouldn't become nonconforming.[5]
No developer had asked. When the mayor asked whether anyone had approached the city about a data center, Planning Manager Dianne York said, "No, this is strictly precautionary." Council Member Joshua Massey said that if the ordinance "gives us the ability to refuse a large data center, then it may be what our citizens are looking for." Staff plan to bring development standards for data centers to the Planning and Zoning Commission next.[5]
# Loudoun County: where the by-right rollback started
Before any of these 24 places, there was Loudoun, the world's biggest data center market, which ended by-right approval in March 2025. Its by-right status started as a gap in the code. In 2000, the county's zoning ordinance had no category for data centers, so the zoning administrator ruled they would be regulated like office buildings. That made them permitted by right anywhere offices were allowed, including office parks next to homes.[6]
At a Board of Supervisors meeting in January 2026, Chair Phyllis J. Randall said:[7]
![]()
Today the county has about 233 data center buildings in operation and 171 more planned. Data centers brought in $1.2 billion in fiscal 2026, 39% of the county budget.[6]
# Why Loudoun ended by-right data center development
As data centers started proliferating, residents pushed back on noise, water use, power lines and how the buildings looked. Loudoun's Board voted in July 2024 to start removing by-right status.[8] On March 18, 2025, it voted 7–2 to make data centers a special exception use everywhere they had been allowed by right. Every new project now needs hearings before the Planning Commission and the Board, and a final Board vote.[8]
Projects already in review were grandfathered, except those within 500 feet of homes.[8] That exemption shows what by-right was worth. At least 17 grandfathered cases, covering more than 11 million square feet, are still moving through the old administrative process.[9]
The Board has used its voting power. In November 2026 it voted 7–1, with one abstention, to pause decisions on new data center and substation applications while it writes new standards, expected in 2027.[8] The grandfathered by-right projects keep moving through staff review. Everything that needs a vote waits.
Now its neighbors are following. Prince William County, next door, had a Data Center Opportunity Zone Overlay that let data centers go up by right on mapped parcels. In September 2026 it moved to shrink that overlay.[10] It's also where one of the region's biggest proposed campuses fell apart; see what happened to the Digital Gateway.
![]()
Prince William County Board of County Supervisors meeting. Source: Prince William County meeting video.
Chesapeake, Virginia took a similar route in August, voting unanimously to end by-right use, with one council member arguing that projects with heavy power and water demands need public input.[1]
# What losing by-right means for developers and investors
Losing by-right changes the risk on a site. A by-right project answers to the code. A special exception or conditional use project answers to a public hearing and a board majority. The cases above show what that means in practice.
The entitlement moves into the meeting room. Zoning a site for data centers no longer guarantees approval. In Orange County and Denison, every project now needs a permit and a public vote. In Manalapan, there's no path at all until the township finishes its review. Underwriting a site now means underwriting the board, not just the code.
Timelines get longer and less certain. A by-right project moves at the speed of plan review. A discretionary one moves at the speed of hearings and votes. In Virginia, for example, a board generally has 12 months to act once a case reaches the Planning Commission.[9] And a board that controls approvals also controls the pace: Loudoun's board paused new applications altogether while it writes new rules.[8]
The rules are still being written. Most of these changes are first steps. Denison's staff are drafting development standards, Manalapan's planning board will decide whether data centers come back under conditions, and Loudoun expects new standards in 2027.[2][5][8] Projects that come in now will be shaped by rules still in draft.
The time to plan is during the debate, not after the vote. These changes don't happen overnight. Loudoun's took eight months, from the July 2024 vote to the March 2025 ordinance.[8] Orange County's took about three and a half months, from January to April 2026.[4] GatherGov's data center app tracks those debates in local meetings, so you can see a by-right change while it's still a proposal.
# Frequently asked questions
What does by-right mean for data centers? By right means a data center is a permitted use in a zoning district. If the project meets the code's standards, staff approve it through site plan review, with no public hearing or board vote. That makes timelines shorter and outcomes more predictable than a special exception or conditional use permit.
Is removing by-right zoning the same as banning data centers? No. GatherGov tracks four kinds of local data center restriction: bans in every zoning district, bans outside named districts, removal of by-right status, and limits on operations such as megawatt size or water use. When by-right status is removed, the use is still allowed, but each project needs approval.[1]
What happens to data center projects already in the pipeline? It depends on the ordinance. Loudoun grandfathered pending applications in 2025, except those within 500 feet of homes.[8] Grandfathering can be challenged later: since August 2026, Loudoun supervisors have been weighing whether to end those exemptions for cases without vested rights.[8]
Did Loudoun County ban data centers? No. In March 2025, Loudoun removed data centers as a by-right use, so every new project needs a special exception approved by the Board of Supervisors. In November 2026 the Board also paused decisions on those applications while it writes new standards, expected in 2027.[8]
Is a special exception the same as a conditional use permit? They work the same way: a discretionary approval after a public hearing, often with conditions. The name changes by state. Virginia uses special exception, while many other states use conditional use permit or special use permit. Who decides also varies, from an appointed board to the elected council.
Which states have the most places ending by-right data center zoning? New Jersey, with seven places in 2026, followed by Virginia and Florida with three each, according to GatherGov's data as of November 18, 2026.[1]
Why don't New Jersey towns pass data center moratoriums? New Jersey's Municipal Land Use Law bars moratoriums on development applications unless a qualified health professional certifies a clear and imminent danger to public health, and caps them at six months.[3] Towns that want time to study data centers usually remove them as a permitted use instead, as Manalapan did in August 2026.[2]
# Footnotes
-
GatherGov data center policy dataset, Nov 18, 2026. https://gathergov.com/industries/data-center ↩ ↩[2] ↩[3] ↩[4] ↩[5] ↩[6]
-
GatherGov meeting data, Manalapan Township Committee, Aug 12, 2026, 00:18:05–00:19:01 (Ordinance 2026-09). ↩ ↩[2] ↩[3]
-
N.J.S.A. 40:55D-90(b), New Jersey Municipal Land Use Law. https://law.justia.com/codes/new-jersey/title-40/section-40-55d-90/ ↩ ↩[2]
-
GatherGov meeting data, Orange County, VA Board of Supervisors, Apr 28, 2026, 00:59:54–01:10:34; Orange County Board of Supervisors agenda packet, Apr 28, 2026 (ZTA 26-01). ↩ ↩[2] ↩[3]
-
GatherGov meeting data, Denison, TX City Council, May 18, 2026, 00:14:47–00:24:28; City of Denison, City Council minutes, May 18, 2026 (Ordinance No. 5448). ↩ ↩[2] ↩[3]
-
Loudoun County, "Data Centers: The Loudoun Story." https://www.loudoun.gov/6408/Data-Centers-The-Loudoun-Story ↩ ↩[2]
-
GatherGov meeting data, Loudoun County Board of Supervisors Business Meeting, Jan 21, 2026, 00:46:37. ↩
-
GatherGov meeting data, Loudoun County Board of Supervisors, 2024–2026. ↩ ↩[2] ↩[3] ↩[4] ↩[5] ↩[6] ↩[7] ↩[8] ↩[9] ↩[10]
-
Office of Supervisor Juli E. Briskman, "Loudoun Board Enacts Pause on Data Centers," Sept 16, 2026. https://www.loudoun.gov/DocumentCenter/View/222331/Statement---Loudoun-Board-Enacts-Pause-on-Data-Centers ↩ ↩[2]
-
GatherGov meeting data, Prince William County Board of County Supervisors, Sept 2026. ↩