Towns aren't saying no to data centers. They're saying where.
A growing number of towns are open to data centers, just not everywhere. GatherGov tracks which districts these communities are opening and the rules they're writing for them: special permits, size caps and buffers from homes. In the 51 places we have tracked so far, nearly half steer data centers to industrial land. For developers, the question is shifting from "Is this town open?" to "Which parcels qualify?"
# How towns are deciding where data centers are allowed
When towns write new data center zoning rules, most land on the same answer: allow development on industrial land, away from homes, usually through a special or conditional use permit. Some places are going further. Instead of opening a whole zone, they are naming the exact parcels or creating new districts built for data centers. Others are regulating size, welcoming smaller facilities and ruling out hyperscale campuses.
51 local governments in 23 states are steering data centers to industrial land and dedicated districts. Pennsylvania leads with 12.
# Why Pennsylvania leads on data center zoning districts
Pennsylvania is an interesting example. State law doesn't allow local governments to ban data centers outright. Instead, towns that want more control can adopt a curative amendment, a pause of up to 180 days on new applications, after which they must specify exactly where data centers will be allowed. So when a Pennsylvania township adopts new data center rules, it is often the end of that process and the town's answer to "where."
Twelve Pennsylvania townships in our data, from the Lehigh Valley to the Poconos, now direct data centers to specific districts. Lower Salford Township created a data center overlay on a set of industrial parcels along the turnpike, while Upper Saucon Township allows them only in its industrial and enterprise overlay zones.
# Three data center ordinances that show where development can go
Among the 51 places we tracked, three stood out for how clearly they outlined data center development. Each took a different approach: one limited data centers to industrial land, one created a dedicated district, and one matched each size of data center to its own district.
# Industrial land only: Massillon, Ohio
Massillon, Ohio, is pointing data centers to its industrial brownfields. In August, the city council voted 7–1 to allow data centers only on I-2 General Industrial land, including former steel sites that have sat empty for years.[1] The ordinance requires a 400-foot setback, and the city's Site Planning Review Committee will review each project for water, electricity, pollution and noise.
![]()
# A dedicated data center district: Town of Grant, Wisconsin
The Town of Grant, a rural town in Portage County, Wisconsin, updated its zoning code and clarified the path for data center development. Its updated zoning ordinance adds an "Industrial 2 Data Center" floating district, a zone written into the code but not yet drawn on the map.[2] When a landowner petitions to rezone a parcel and the town and county approve it, the district lands on that site and a data center can move forward with a conditional use permit. In October, Portage County's Planning and Zoning Committee approved the changes unanimously, with residents speaking in favor.[3]
![]()
# Zoned by size: Mount Airy, North Carolina
Mount Airy, North Carolina, made room for data centers of every size, each in its own district. Under an ordinance adopted in October, micro data centers under 5,000 square feet can locate in the city's highway and medical business districts as well as its industrial district, while larger facilities are directed to the M-1 Industrial District.[4]
For developers, the rules spell out exactly what to plan for from day one: closed-loop cooling, a connection to the public water system, a 65-decibel noise limit at the property line, and buffers of 500 feet from homes and 1,000 feet from schools.
![]()
# What data center zoning means for site selection
The question has changed. In a growing number of communities, the answer to data centers isn't yes or no. It's where. For developers, that means site selection now happens at the district level: a town can make headlines for restricting data centers while specific parcels remain open.
Industrial land is the default. Nearly half of the 51 communities steer data centers to industrial zones, often brownfields and sites with existing infrastructure. Projects that start there start with fewer obstacles.
Clear rules mean predictable approvals. Setbacks, noise limits and water requirements tell developers exactly what a successful application looks like.
More rules are coming. Two-thirds of these rules were adopted since July 2026, and many communities are still writing theirs. Knowing which districts are open before an ordinance passes is a head start.
GatherGov is tracking all 51 communities and the districts where data centers are allowed. Reach out on LinkedIn for the full list, or explore the data center policy data.
# FAQ
# Where are data centers allowed to be built?
In the 51 communities GatherGov tracked that limit data centers to specific districts, nearly half allow them only on industrial land, usually through a special or conditional use permit. Others name exact parcels, create dedicated data center districts, or set districts by facility size.
# Can a Pennsylvania town ban data centers?
No. Pennsylvania state law doesn't allow local governments to ban data centers outright. Towns that want more control can adopt a curative amendment, a pause of up to 180 days on new applications, after which they must specify where data centers will be allowed.
# What is a floating zoning district for data centers?
A floating district is written into the zoning code but not drawn on the zoning map. In the Town of Grant, Wisconsin, the "Industrial 2 Data Center" district lands on a specific parcel only after a landowner petitions to rezone it and the town and county approve.
# What rules do data center ordinances typically include?
Common requirements include setbacks or buffers from homes and schools, noise limits at the property line, water and cooling requirements, and review of each project through a special or conditional use permit.
# Footnotes
-
City of Massillon, Ohio, City Council meeting minutes, August 3, 2026 (Ordinance No. 60-2026). https://massillonohio.gov/wp-content/uploads/08-03-2026-Council-Mtg.pdf ↩
-
Town of Grant, Portage County, Wisconsin, Zoning Ordinance 2026-01, Industrial 2 Data Center District. https://townofgrant-portage.wi.gov/planning-zoning/ ↩
-
Portage County, Wisconsin, Planning and Zoning Committee meeting minutes, October 27, 2026 (REQ-2026-018 and REQ-2026-019). https://portagecowi.portal.civicclerk.com/event/9190/media ↩
-
City of Mount Airy, North Carolina, Board of Commissioners agenda packet, October 15, 2026 (Ordinance No. 2027-013). https://www.mountairy.org/AgendaCenter/ViewFile/Agenda/_10152026-827 ↩