A development permit is any local approval that lets land be developed. It is a category of approvals, not one document.

Published on August 21, 2026, authored by

ELEvelyn Lifton
What Is a Development Permit? Types, Deadlines, and Order vs Permit

A development permit is any local approval that allows lands to be developed. The term is a category, not a single document; it includes building permits, zoning permits, subdivision approvals, rezonings, special exceptions, and variances in most definitions. The ultimate decision made after applications is called a development order.[1]

# How a Development Permit Works

Understanding the overall function of the development permitting process is crucial because a single project could require several permits, in sequence, from entirely different bodies. A subdivision might need a rezoning from the council, a plat approval from the planning commission, and building permits from the building department---each a development permit in its own right.

Florida sets statutory deadlines that show the actual shape of the process for municipalities:[2]

  1. Receipt confirmed within 5 business days
  2. Written completeness determination within 30 days
  3. If the application is deficient, the applicant has 30 days to supply what is missing
  4. Decision within 120 days of the application being deemed complete
  5. Decision within 180 days instead, if final action requires a public or quasi-judicial hearing
  6. Written findings supporting the decision, either way

There are two important things to note about development permits. The first is that a denial must cite the ordinance, rule, or statute it rests on, which forces the reasons onto the record. The second is that the clock starts when the application is deemed complete, not when it is initially filed. As a result, the timeline can end up being longer than initially expected

Additionally, on top of all other regulations, the decision must also conform to the local comprehensive plan, which constrains the permit and all development in the area.[3]

# Common Snags in Getting a Development Permit

The complex sequence is where most projects lose months. Approvals all depend on each other, and the wrong order means waiting on a decision that cannot be made yet. A conditional use hearing scheduled ahead of the rezoning it depends on is a wasted hearing.

The completeness loop is the second cost center. Because deadlines start at completeness rather than filing, a request for more information resets your expectations without breaking any deadline. Front-loading the application is the cheapest time savings available.

Each permit type has its own decision-maker, which determines what a favorable outcome requires. Staff approvals turn on meeting written standards. Approvals that reach an elected body turn on that plus politics, and those appear on published agendas. GatherGov makes local agendas and meeting records searchable across jurisdictions, so you can see when an approval is calendared for a vote.

  • Conditional use permit: approval for a use a district allows only with conditions attached
  • Special use permit: the same instrument under the name used in New York and other states
  • Site plan review: technical review of layout, access, drainage, and parking
  • Rezoning: changing a parcel's zoning classification

# Frequently Asked Questions

# What is the difference between a development permit and a building permit?

A building permit authorizes construction under the building code. Development permit is the broader category of land use approvals, which in many statutes includes building permits alongside rezonings, variances, and plat approvals. Some statutes carve building permits out, so read the definition in the section you rely on.

# What is a development order?

The development order is the local government's official decision on an application for a development permit, which is either granting it, granting it with conditions, or denying it entirely. The permit is what you ask for, and the order is what you receive: a document that carries the conditions and appeal rights.

# How long does a development permit take?

The timeline depends heavily on where it is submitted. In Florida municipalities, it is typically 120 days after the application is deemed complete, or 180 days if final action requires a public or quasi-judicial hearing. Other states set their own limits or none at all. The number that matters locally is how long comparable applications actually took, not the statutory ceiling.

# Do I need more than one development permit for a project?

Usually, yes. Regardless of size, most projects have to stack several approvals from different bodies. For example, many stack a rezoning, site plan approval, plat, and building permits on one project. The single most useful planning step for developers is to map the sequence and determining who is actually making the decision for each one before filing anything.


# Footnotes

  1. Fla. Stat. § 163.3164, defining "development order" as any order granting, denying, or granting with conditions an application for a development permit, and "development permit" as including any building permit, zoning permit, subdivision approval, rezoning, certification, special exception, variance, or any other official action of local government having the effect of permitting the development of land. See also Fla. Stat. § 380.031(3) and (4).

  2. Fla. Stat. § 166.033, Development permits and orders (2025), setting receipt, completeness, and decision timeframes for municipalities, requiring written findings and citation of legal authority for denials, and excluding building permits from the terms as used in that section. https://www.flsenate.gov/Laws/Statutes/2025/166.033

  3. Fla. Stat. § 163.3194, providing that actions taken in regard to development orders must be consistent with the adopted comprehensive plan; discussed in Florida Attorney General opinion on comprehensive plan conformance. https://www.myfloridalegal.com/ag-opinions/comprehensive-plan-ordinance-conformance

Author

  • EL

    Evelyn Lifton

    Evelyn Lifton is a researcher at GatherGov, where she focuses on the intersection of public opinion, local government, and real estate.